REMS Programme Research and Development

The purpose of the …REMAC.

The SGM Project:

  • foresees to procure thirty (30) 2 new Site Gate Monitors to replace and complete the current SGM systems,
  • is planned to start in 2021 and last five years until completion,
  • has an estimated budget of 1’200’000 CHF without contingency,
  • has a human resource forecast estimated to about 8 man-years.

The purpose of the GRAMS consolidation evaluation project is to achieve:

  • Delivery of consolidated technical requirements.
  • Delivery of a proof-of-concept prototype.
  • Delivery of a consolidated cost estimation for the final design and series production.